World fab map
Where the world’s chips are made: the biggest chip factories, memory plants, and packaging sites, with what each one makes and where it stands today.
A chip factory, or fab, costs tens of billions of dollars and takes years to build, so where they go says a lot about where the industry is heading. This map shows the most important sites in Asia, the United States, and Europe, including the ones still being built and the ones that were delayed or dropped. Each entry links to the news report or company page behind it.
Three kinds of site are shown. Logic fabs make processors and most other chips. Memory fabs make DRAM, HBM, and flash storage. Packaging plants put finished dies together into the parts that go into phones, PCs, and servers, which has become a bottleneck of its own (see What is CoWoS?).
68 sites in 14 countries: 39 logic fabs, 17 memory fabs, and 12 packaging plants. Last checked Nov. 28, 2026.
Tap or click a dot to see the plant. Use the buttons to zoom in on Asia, Taiwan, North America, or Europe.
Every site on the map
| Site | Place | Kind | Makes | Status | Source |
|---|---|---|---|---|---|
| TSMC Fab 12 (Hsinchu) | Hsinchu, Taiwan | Logic | Chip production and TSMC’s main research center | Long-running Hsinchu site that also houses TSMC’s head office and R&D center; more phases were being added as of 2026. | Wikipedia |
| TSMC Fab 14 (Tainan) | Tainan, Taiwan | Logic | Older-generation chips (about 40 to 90 nm) | TSMC plans to cut its older-chip capacity here by 15% to 20% by 2028 (January 2026 report). | Counterpoint |
| TSMC Fab 15 (Taichung) | Taichung, Taiwan | Logic | 7 nm and 28 nm chips | In June 2026, part of the site (Fab 15A) was reported to be shifting from 28 nm to 4 nm, while Fab 15B keeps making 7 nm chips. | TrendForce |
| TSMC Fab 18 (Tainan) | Tainan, Taiwan | Logic | 3 nm and 5 nm chips | Has made 3 nm chips in volume since late 2022; some 5 nm lines were being converted to 3 nm in 2026. | Tom’s Hardware |
| TSMC Fab 20 (Baoshan) | Hsinchu, Taiwan | Logic | 2 nm chips | Ramping The first two phases were ramping up 2 nm production as of mid-2026; phases 3 and 4 are under construction. | Tom’s Hardware |
| TSMC Fab 22 (Kaohsiung) | Kaohsiung, Taiwan | Logic | 2 nm chips | Ramping Began 2 nm volume production in late 2025; phases 2 and 3 were set to ramp in the second half of 2026. | Tom’s Hardware |
| TSMC Fab 25 (Taichung) | Taichung, Taiwan | Logic | 1.4 nm (A14) chips | Under construction Work began in late 2025, with test production expected in late 2027 and volume output in the second half of 2028. | TrendForce |
| TSMC Advanced Packaging Fab 6 (Zhunan) | Zhunan, Taiwan | Packaging | 3D chip stacking (SoIC) and other advanced packaging | Being expanded in 2026 and could approach 10,000 stacked-chip wafers a month, per a June 2026 report. | Tom’s Hardware |
| TSMC Advanced Packaging Fab 7 (Chiayi) | Chiayi, Taiwan | Packaging | Advanced packaging for phone and AI chips | Ramping Its second building was due to start production in 2026, with the first building following in 2027. | TrendForce |
| TSMC Advanced Packaging Fab 8 (Tainan) | Tainan, Taiwan | Packaging | CoWoS packaging for AI chips | Ramping A former display plant expected to top 40,000 CoWoS wafers a month by late 2026. | Tom’s Hardware |
| UMC Fab 12A (Tainan) | Tainan, Taiwan | Logic | Mature and specialty chips down to 14 nm | UMC’s main 12-inch fab, in volume production since 2002. | UMC |
| Samsung Pyeongtaek campus (P1 to P5) | Pyeongtaek, South Korea | Memory | DRAM, HBM, NAND flash, and some foundry chips | The P4 building came online in 2026, and foundation work on P5 is underway with completion targeted for 2030. | TrendForce |
| Samsung Hwaseong campus | Hwaseong, South Korea | Memory | DRAM | In August 2026, Samsung began adding DRAM capacity using idle cleanroom space at its H1 complex. | TrendForce |
| Samsung Giheung NRD-K research complex | Yongin, South Korea | Logic | Advanced chip research; a 2 nm line for HBM base chips is under study | The first research line was finished in late 2024; a second line is under construction and targeted for late 2028. | TrendForce |
| Samsung Onyang HBM packaging line | Asan, South Korea | Packaging | HBM packaging | Under construction Broke ground on a new HBM line at the Onyang packaging campus on Nov. 12, 2026, aiming to start by June 2028. | Korea JoongAng Daily |
| SK hynix Icheon campus (M14, M16) | Icheon, South Korea | Memory | DRAM | The M16 fab installed the industry’s first commercial High-NA EUV tool in September 2025 for future DRAM. | Tom’s Hardware |
| SK hynix M15X (Cheongju) | Cheongju, South Korea | Memory | DRAM for HBM | Ramping SK hynix planned to start putting wafers into the new fab in February 2026, months ahead of schedule. | The Star (Reuters) |
| SK hynix P&T7 packaging plant (Cheongju) | Cheongju, South Korea | Packaging | HBM packaging and testing | Under construction Broke ground on April 22, 2026; the test line is due in October 2027 and the packaging line in February 2028. | TrendForce |
| SK hynix Yongin cluster (Fab Y1) | Yongin, South Korea | Memory | DRAM, including HBM | Under construction The first cleanroom is targeted for February 2027, and a second fab is set to break ground in July 2027. | Blocks and Files |
| TSMC (JASM) Kumamoto Fab 1 | Kikuyo, Japan | Logic | 12 to 28 nm chips for cars and industrial uses | Turned its first quarterly profit in early 2026 and was gradually resuming work after a July 28, 2026, earthquake. | Tech Times |
| TSMC (JASM) Kumamoto Fab 2 | Kikuyo, Japan | Logic | 3 nm chips | Under construction Japan approved a switch to 3 nm in October 2026, with production expected to start around December 2028. | TechNews |
| Rapidus IIM-1 (Chitose) | Chitose, Japan | Logic | 2 nm chips | Ramping A pilot line has run since April 2025; mass production is targeted for the second half of fiscal 2027. | Tom’s Hardware |
| Kioxia Yokkaichi plant | Yokkaichi, Japan | Memory | 3D NAND flash memory | Kioxia’s main flash plant; its newest building (Fab 7) was running at about half capacity in June 2026. | TrendForce |
| Kioxia and Sandisk Kitakami plant (Fab 1, Fab 2) | Kitakami, Japan | Memory | 3D NAND flash memory | Ramping Fab 2 started operating in September 2025, with meaningful output expected in the first half of 2026. | Kioxia |
| Micron Hiroshima fab | Higashihiroshima, Japan | Memory | DRAM and HBM | Broke ground on an expansion on July 4, 2026, with new equipment due in the second half of 2028. | TrendForce |
| SMIC SMIC Shanghai | Shanghai, China | Logic | Contract-made logic chips; SMIC started its 14 nm production in Shanghai in 2019 | SMIC ran at 93.7% of capacity across its fabs in the second quarter of 2026 and is looking at adding tools in existing buildings (August 2026). | TrendForce |
| SMIC SMIC Beijing | Beijing, China | Logic | Contract-made chips on 28 nm and older processes, plus specialty processes for RF and high-voltage chips | Ramping A second 12-inch line in Beijing’s development zone entered mass production in July 2026, two months early, aiming for 35,000 wafers a month by end-2026. | SETMM |
| Hua Hong Hua Hong Wuxi (Fab 7 and Fab 9) | Wuxi, China | Logic | Contract-made power, analog, and other specialty chips on 12-inch wafers | Ramping Fab 9A was installing tools and aiming for full capacity by late Q3 2026; a third phase (Fab 9B) began construction in March 2026 (September 2026). | 10jqka |
| Hua Hong (Huali) Huali Shanghai (Fab 5 and Fab 6) | Shanghai, China | Logic | Contract-made logic chips on 65 nm to 40 nm processes, with a 7 nm process in test production | Reuters reported in March 2026 that Huali was test-producing 7 nm chips, reportedly with Huawei’s help, aiming for a few thousand wafers a month by year-end. | Dawn (Reuters) |
| CXMT CXMT Hefei | Hefei, China | Memory | DRAM memory chips, including DDR5 and LPDDR5 for PCs, servers, and phones | CXMT listed its shares in Shanghai on July 27, 2026, and is using the money to upgrade and expand its DRAM lines. | TrendForce |
| YMTC YMTC Wuhan | Wuhan, China | Memory | 3D NAND flash storage chips, about 270 layers; the newest phase will also make some DRAM | Fabs 1 and 2 run about 200,000 wafers a month, and a third phase was due to start operating in late 2026 (April 2026). | Tom’s Hardware |
| Samsung Samsung Xi’an | Xi'an, China | Memory | NAND flash storage chips; China makes about 30% to 35% of Samsung’s NAND | Samsung is upgrading the plant to newer 286-layer NAND in coordination with Washington, Reuters reported (October 2026). | TrendForce |
| SK hynix SK hynix Wuxi | Wuxi, China | Memory | DRAM memory chips, recently moved to a newer 1a process for products like DDR5 | SK hynix doubled its Wuxi spending to 581 billion won in 2025, mostly on equipment (March 2026). | TrendForce |
| SK hynix (Solidigm) SK hynix Dalian | Dalian, China | Memory | NAND flash storage chips at the former Intel plant, bought in 2021 | Fab 1 runs about 100,000 wafers a month; a second fab restarted and targets mass production in the first half of 2027 (August 2026). | TrendForce |
| TSMC TSMC Nanjing (Fab 16) | Nanjing, China | Logic | Contract-made chips on 16/12 nm and 28/22 nm processes, largely for cars and other specialty uses | The U.S. granted TSMC a yearly license for Nanjing tool shipments before its earlier waiver ended on Dec. 31, 2025. | Yahoo (Reuters) |
| Micron Micron Singapore NAND fabs | Singapore (Woodlands), Singapore | Memory | NAND flash storage chips; a new $24 billion fab is being added at the same site | Micron broke ground on a new NAND fab in January 2026 and expects it to start output in the second half of 2028. | The Register |
| GlobalFoundries GlobalFoundries Singapore | Singapore (Woodlands), Singapore | Logic | Contract-made RF, power, silicon photonics, and other specialty chips on 200mm and 300mm wafers | The Singapore fabs were reported running above 90% of capacity as demand for AI-related silicon photonics grows (September 2026). | AnySilicon |
| UMC UMC Fab 12i | Singapore (Pasir Ris), Singapore | Logic | Contract-made chips on 22 nm and 28 nm for displays, low-power memory, and wireless connections | Ramping UMC opened its new expansion in April 2025, with the first phase set to start volume production in 2026. | Singapore EDB |
| VSMC (Vanguard and NXP) VSMC Singapore | Singapore (Tampines), Singapore | Logic | Contract-made analog, power management, and mixed-signal chips on 130 nm to 40 nm, on 300mm wafers | Ramping VSMC opened the fab on Sept. 28, 2026; it is in trial production, with volume production set for early 2027. | Singapore EDB |
| Intel Intel Penang advanced packaging | Penang, Malaysia | Packaging | Assembles, tests, and packages advanced chips, including multi-chip designs, next to Intel’s older Penang plants | Under construction The new packaging plant was set to begin operations in 2026, according to a September 2026 report. | Tech Wire Asia |
| Infineon Infineon Kulim (Module 3) | Kulim, Malaysia | Logic | Silicon carbide and gallium nitride power chips for electric cars, solar power, and trains | The first phase opened in August 2024; a second phase of up to 5 billion euros will grow it into a large 200mm silicon carbide fab. | eeNews Europe |
| Tata Electronics (with PSMC) Tata Dholera fab | Dholera, India | Logic | India’s first large chip factory, planned for 28 nm to 110 nm, starting with older 90 nm and 55 nm processes | Delayed India’s technology minister said commercial production is now expected in mid-2028, not end-2026 (July 2026). | TrendForce |
| Micron Micron Sanand | Sanand, India | Packaging | Assembles and tests DRAM memory and SSD storage products from wafers made elsewhere | Ramping Micron opened the plant on Feb. 28, 2026, expecting tens of millions of chips in 2026 and hundreds of millions in 2027. | TrendForce |
| Tata Electronics Tata Assam (Jagiroad) | Jagiroad, India | Packaging | Assembles, packages, and tests chips for cars, phones, and telecom gear, including Qualcomm car modules | Ramping Trial production began at about a quarter of planned capacity, with commercial output expected in December 2026 or January 2027 (October 2026). | The Federal |
| TSMC TSMC Arizona | Phoenix, United States | Logic | 4 nm chips now; 3 nm and 2 nm planned | The first fab has made 4 nm chips since 2024; TSMC said in October 2026 that the second fab will start 3 nm volume production in the third quarter of 2027, and the third fab is under construction. | AZ Big Media |
| Intel Intel Fab 52 (Ocotillo campus) | Chandler, United States | Logic | Intel 18A chips (Panther Lake, Clearwater Forest) | Ramping Fab 52 became fully operational in October 2025 and is ramping 18A output; the neighboring Fab 62 began tool installation in October 2026 and targets late 2028. | Tom’s Hardware |
| Intel Intel Oregon (D1X) | Hillsboro, United States | Logic | Research and development of new chipmaking processes, including 14A | Intel’s main research fab installed the first commercial High-NA EUV tool and, as of October 2026, uses it in making Panther Lake chips. | TrendForce |
| Intel Intel Ohio One | New Albany, United States | Logic | Advanced chips (process not yet named) | Delayed Originally due in 2025-2026, the first fab is now expected in 2030-2031; workers set its first major roof truss in October 2026. | TrendForce |
| Intel Intel Fab 9 (Rio Rancho) | Rio Rancho, United States | Packaging | 3D chip stacking (Foveros) and chiplet packaging (EMIB) | Opened in January 2024; Intel described it in July 2026 as its leading U.S. advanced packaging site. | Intel |
| Intel Intel Ireland (Fab 34) | Leixlip, Ireland | Logic | Intel 4 and Intel 3 chips for Core Ultra and Xeon 6 | In July 2026 Intel announced a 5 billion euro upgrade, after buying back full ownership of Fab 34 in April 2026. | Tom’s Hardware |
| Intel Intel Kiryat Gat (Fab 28) | Kiryat Gat, Israel | Logic | Intel 7 chips, including parts for Xeon server processors | A gas explosion on Oct. 14, 2026, injured workers and shut the fab; production was restarting at the end of October. | The Times of Israel |
| Intel Intel Magdeburg | Magdeburg, Germany | Logic | Planned advanced chip fab (never built) | Canceled Intel canceled the planned megafab in July 2025. | The Register |
| Intel Intel Poland (Wroclaw) | Wroclaw, Poland | Packaging | Planned chip assembly and testing plant (never built) | Canceled Intel canceled the planned assembly and test plant in July 2025. | The Register |
| Samsung Samsung Taylor | Taylor, United States | Logic | 2 nm chips, including Tesla’s AI chips | Ramping As of October 2026, the first fab was set to begin operations in late 2026 with volume production in 2027, and a second fab was planned for 2030. | TechPowerUp |
| Samsung Samsung Austin | Austin, United States | Logic | Older-generation chips (65 nm to 14 nm) such as image sensors, SSD controllers, and display drivers | Samsung’s first U.S. fab, running since 1996. | VLSI.kr |
| Micron Micron Boise | Boise, United States | Memory | DRAM memory chips | Under construction As of October 2026, the first new fab is expected to produce its first wafers in mid-2027 and a second fab in late 2028. | Idaho News |
| Micron Micron New York | Clay, United States | Memory | DRAM memory chips | Under construction Micron broke ground in January 2026; the first fab could start operating in early 2029, with real output around 2030. | Tom’s Hardware |
| Micron Micron Manassas | Manassas, United States | Memory | DRAM memory for cars, defense, and industrial uses | Micron began making newer 1-alpha DRAM here in May 2026 and expects qualified production by the end of 2026. | Micron |
| GlobalFoundries GlobalFoundries Fab 8 | Malta, United States | Logic | FinFET, FD-SOI, RF, and silicon photonics chips | In October 2026, Japan agreed to fund two new fabs at the site, with the first expected to open in 2029. | Spectrum News |
| GlobalFoundries GlobalFoundries Dresden | Dresden, Germany | Logic | Specialty chips for cars, industry, and defense | An expansion reached its topping-out in October 2026 and aims to lift output to over 1 million wafers a year by the end of 2028. | Unite.AI |
| Texas Instruments TI Sherman (SM1) | Sherman, United States | Logic | Analog and embedded processing chips | Ramping The first of up to four fabs began production in December 2025. | Texas Instruments |
| ESMC (TSMC, Bosch, Infineon, NXP) ESMC Dresden | Dresden, Germany | Logic | 28/22 nm and 16/12 nm chips, mainly for cars and industry | Under construction The building was topped out in September 2026, and the first production tools are due in the second half of 2027. | Focus Taiwan |
| Infineon Infineon Dresden Smart Power Fab | Dresden, Germany | Logic | Power and analog chips for cars, renewable energy, and data centers | Ramping Infineon opened the 5 billion euro fab in July 2026, several months ahead of schedule. | electrive |
| STMicroelectronics STMicroelectronics Crolles | Crolles, France | Logic | Digital chips and optical connection chips for data centers | In November 2026, ST listed upgrades to its Crolles 300 mm fab for digital and cloud optical chips among its investments. | SEC |
| STMicroelectronics STMicroelectronics Catania Silicon Carbide Campus | Catania, Italy | Logic | Silicon carbide power chips and modules | Ramping ST said in November 2026 that its new 200 mm silicon carbide production in Catania had entered the ramp-up phase. | SEC |
| SK hynix SK hynix Indiana | West Lafayette, United States | Packaging | Packaging of high-bandwidth memory (HBM) for AI chips | Under construction As of August 2026, the cleanroom is due by October 2028 and mass production in the second half of 2029. | The Next Web |
| Amkor Amkor Arizona | Peoria, United States | Packaging | Advanced chip packaging and testing | Under construction Amkor broke ground in October 2025 and in September 2026 raised its planned investment to $12 billion. | ABC15 |
| Wolfspeed Wolfspeed Mohawk Valley | Marcy, United States | Logic | Silicon carbide power chips on 200 mm wafers | Wolfspeed moved its chip production here after closing its older Durham fab in late 2025, following its exit from bankruptcy in September 2025. | Compound Semiconductor |
No sites match those filters.
Locations are approximate. This is a selection of major sites, not every plant in the world. Spot a mistake or a missing fab? Write to contact@chipdecoder.com.